When reserving the land, the electronic contract must be signed within 48 hours so that the land is not canceled from the beneficiary.
Special Land:
The building permit must be obtained and uploaded to “Sakani” site and construction begins within 6 months from completion of the allocation; then the construction is completed and occupation certificate is issued within 3 years
Normal land:
The building permit must be obtained and uploaded to “Sakani” site within 6 months from the completion of the allocation; then construction must be commenced within a year and the construction is completed and occupation certificate is issued within 3 years.