What is the time limit for completing the land product procedures?

When reserving the land, the electronic contract must be signed within 48 hours so that the land is not canceled from the beneficiary.

Special Land:

The building permit must be obtained and uploaded to “Sakani” site and construction begins within 6 months from completion of the allocation; then the construction is completed and occupation certificate is issued within 3 years

Normal land:

The building permit must be obtained and uploaded to “Sakani” site within 6 months from the completion of the allocation; then construction must be commenced within a year and the construction is completed and occupation certificate is issued within 3 years.